ADR 0002: Outcome-gated phases instead of time-boxed weeks

  • Status: Accepted
  • Date: 2026-09-10
  • Deciders: AlphaNerdFx

Context

The original roadmap divided twelve weeks of work into nine numbered phases. Week 0 was planned as one week and finished in thirteen hours, across eighteen commits, using agents working in parallel on disjoint files.

The obvious response is to divide every remaining estimate by seven. That would be wrong, and the composition of Week 0 shows why.

Category Lines produced
Documentation 3,182
Configuration and CI 732
Tests 474
Product code 202

Roughly 85 percent of the output was documentation and configuration. That work is well specified, has no external dependencies, is verifiable by a linter or a schema, and splits cleanly across files. Those four properties are exactly what makes work compressible by agents.

The remaining phases do not share those properties.

What actually limits each kind of work

Network-bound work does not compress at all. This project is bound by a compliance rule of one request per second to stats.nba.com. Possession data for stint extraction needs play-by-play per game, and the floor is arithmetic:

Scope Requests Wall-clock floor
2015 to 2024, one request per game 12,300 3.4 hours
2015 to 2024, two requests per game 24,600 6.8 hours
2002 to 2026, one request per game 30,750 8.5 hours
2002 to 2026, two requests per game 61,500 17.1 hours

Twenty agents finish that in the same time as one. The constraint is a rule this project chose to honour, and honouring it costs hours that no amount of parallelism recovers.

Compute-bound work compresses only with better algorithms. A cross-validated ridge solve over a sparse design matrix with a couple of thousand player columns and millions of stint rows, bootstrapped for standard errors, is CPU time. More agents writing code does not shorten it.

Judgement does not compress. The RAPM validation gate asks whether a computed metric agrees closely enough with a published one to be trusted. If it does not, somebody has to decide between debugging and switching the target variable. That is a decision, not a task.

Review capacity moves in the wrong direction. The maintainer is the human checker. Agents raise the volume of code needing review without raising the capacity to review it. Past a point, more agents make the bottleneck worse rather than better.

Decision

Replace numbered weeks with phases gated by verifiable outcomes.

Each phase declares:

  1. Entry condition. What must be true before it can start. This makes the dependency graph explicit, so what can run in parallel is visible rather than guessed.
  2. Definition of done. A condition a machine or a person can check, not a feeling that the phase seems finished.
  3. What limits it. One of: agent-parallel, network-bound, compute-bound, judgement, or review-bound. This says directly whether adding agents helps.

Time estimates are dropped. They were fiction before Week 0 and they are fiction at a different scale now. A phase is finished when its exit condition holds.

Consequences

Gained: the dependency graph is explicit, so parallelism is a scheduling fact rather than an aspiration. A phase that says network-bound will not have four agents thrown at it.

Gained: progress becomes checkable. "Phase 2 is done" now means a specific correlation cleared a specific threshold, rather than a week having elapsed.

Lost: no calendar date to point at. For a solo research project with no external deadline this costs little, and a date derived from fictional estimates was never worth pointing at.

Accepted: some phases will take longer than the week they replaced. The network floor above is roughly a working day of waiting on its own, and pretending otherwise would only move the surprise later.